Pacific Palisades · Permit data updated July 28, 2026

The Palisades is being rebuilt, house by house.

Eighteen months after the fire, 985 homes are under construction and 30 families have their keys back. This is an independent account of where the rebuild actually stands — compiled from public permit records, with every figure sourced and dated.

Homes finished

30

Certificates of occupancy issued out of 6,837 structures destroyed —0.4% of what was lost.

As of July 28, 2026 · Pali Rebuild Map / Palisadian-Post

Where the rebuild stands

1,723 applications. 30 finished homes.

The distance between those two numbers is the rebuild. Each stage below narrows — from paperwork filed, to permits in hand, to ground broken, to a family legally able to move back in.

Permits submitted1,723
Applications filed with LADBS to rebuild a home destroyed by the fire.25.2% of homes lost
Permits issued1,158
Plans approved and permits pulled. The owner is cleared to build.16.9% of homes lost
Homes under construction985
Ground broken — grading, foundation or framing underway.14.4% of homes lost
Homes finished30
Certificates of occupancy issued. Legally habitable, keys in hand.0.4% of homes lost

Funnel figures as of July 28, 2026, derived by us from the parcel-level permit records compiled by the Pali Rebuild Map / Palisadian-Post — an independent tracker built by Palisades resident Kevin Pazirandeh from public Los Angeles County records. We count distinct rebuild parcels that have reached each stage; any discrepancy with their published totals is ours, not theirs. Bars are scaled against 6,837 structures destroyed by the Palisades Fire (Shovels permit analysis); not every destroyed structure was a single-family home, so these percentages describe scale rather than an exact completion rate.

What was lost

6,837Structures destroyedBuildings lost to the Palisades Fire across the Palisades and Malibu.As of March 17, 2026 · Shovels permit analysis

The January 2025 Palisades Fire destroyed 6,837 structures and killed twelve people. Permit volume in ZIP 90272 has run roughly 3.7 times its pre-fire annual rate ever since.

A Pacific Palisades lot cleared to bare soil after the fire, a skid-steer loader parked at the edge and the twisted remains of a neighboring structure still standing behind it.
A cleared lot in the fire area. Debris certification is the gate every rebuild waits behind — no permit is issued without it.
Full status and neighborhood breakdown

By neighborhood

The rebuild is not moving at one speed.

The Alphabet Streets have issued nearly a third of recent permits. The Highlands has sold more lots than anywhere else. Terrain, covenants and coastal review explain most of the difference.

Compare all eight side by side, including permits, lot sales and permit path.

More on who they are and what they have built here: Farnsworth Builders in the Palisades.